Period (Date of Loan Agreement):
    March 31, 2004
Place:
    Jakarta
Amount Provided:
    58,679 million Yen
Executing Agency:
    State Electricity Company (PT PLN)
Key Points:
    Strengthening power supply capacity in the Java-Bali power system in response to concern over power shortage.
Outline:
The objective of the project is to strengthen power capacity and improve the stability of power supply. The project consists of newly constructing gas-fired combined cycle power generation units (with a total capacity of 720 MW: 3 turbines) in the Tanjung Priok Plant near Jakarta. The project is due to be completed in 2011.