Keramasan Power Plant Extension Project

Period (Date of Loan Agreement):
    March 31, 2005

Place:
    South Sumatra

Amount Provided:
    9,736 million Yen

Executing Agency:
    State Electricity Company (PT PLN)

Key Points:
    Meeting fast-growing power demand in South Sumatra

Outline: The objective of the project is to mitigate the tight power supply situation and improve the stability of power supply in the South Sumatra power system by constructing additional gas-fired combined cycle power generation facilities (capacity: 80 MW) in the Keramasan Power Plant, South Sumatra Province. This will lead to an improved investment climate and thereby contribute to economic development in the southern region of Sumatra Island.