Period (Date of Loan Agreement):
    March 31, 2005
Place:
    Banten, West Java, East Java
Amount Provided:
    4,287 million Yen
Executing Agency:
    Directorate General Of Highways (Bina Marga) Ministry of Public Works
Key Points:
    Constructing flyovers at major intersections to increase road transport capacity in northern Java
Outline:
The objective of the project is to enhance the transport capacity of North Java Corridor, which provides east-west linkage in northern Java Island, for mitigating traffic congestion and thereby improve the investment climate in the Java region. The project consists of constructing flyovers that carry both road and railway traffic at six intersections along the North Java Corridor and its alternative routes: Merak, Balaraja, Nagreg, Gebang, Peterongan, and Tanggulangin. The project is due to be completed by 2010. Special Terms for Economic Partnership (STEP) has been applied to this project.